Client: West Arnhem Regional Council Project: $583,000 Duration: 8 weeks |
Project Overview: This Project Consists of the following works: • Stone Pitching and concrete works • Drainage upgrades • Roadworks The first stage of the works consisted of installing 24 culverts, Cleaning and Shaping the drains to let the water flow and increase the drainage capacity: |
![](https://northernprojects.net.au/wp-content/uploads/2021/10/Warruwi-Drainage-Works-And-Roadworks-1.jpg)
Stone pitching and concrete works:
The Second stage of the works consisted of stone pitching works to protect the drains from scouring. Concrete margins with weep holes were constructed along a 2 km road to assist in subsurface drainage.
2 concrete floodways were also installed.
![](https://northernprojects.net.au/wp-content/uploads/2021/10/project01-image.jpg)
The third stage of the works consist of 1km of road works with concrete margins on both sides and a 2 coat 7mm/14mm spray seal.